This work is part of the extension of the RER E line to the west of Paris, a sustainable mobility solution that will benefit more than 650,000 passengers every day.
"This is a major milestone for Eiffage Rail, which is involved in a number of major urban projects in Paris. This operation has been a success, thanks in particular to the successful coordination with our partner NGE and the relationship of trust with our customer SNCF Réseau". Nicolas AUBERT, Head of Major Urban Projects and Greater Paris Eiffage Rail.
In figures, this project represents :
- 28 km of track, including 12 km of ballast track and 16 km of concrete track
- 1 overhead section and 1 tunnel section
- 3 new stations crossed
- 3 turnouts
- 350 employees at peak activity
Congratulations to all our teams working on this major project!
More than 100,000 hours of social integration work were carried out on this site!
Consortium: TSO (leader), Eiffage Rail, TSO caténaires and SAGES Rail.
-
19.06.2024Laying of the Foundation Stone for the Future Villeneuve...This Tuesday, June 18, 2024, the foundation stone for the future Villeneuve Demain Technicentre (94) was laid in the presence of Valérie Pécresse, Jean-Pierre Farandou,...
-
07.06.2024Eiffage Rail procède au renouvellement de 35 km de...Nos équipes procèdent au renouvellement de 35 km de voies avec l’aide du train-usine TCM60 et de la dégarnisseuse RM800 !
-