For this project, nearly 10 months of work will be required, with 5,000 m³ of concrete to be poured on site, 4,650 m² of fireproof walls, 5 meters high, to be installed, and 50 workers to be mobilized at peak times.
This new facility will produce hydrogen through water electrolysis, powered by green electricity, with an output of 2,800 tons per year (20 MW in the first phase)!
The production unit will supply heavy transportation in the region (maritime, land, river, and rail), positioning the area as a key player in the energy transition by preventing the emission of 28,000 tons of CO₂ equivalent per year.
Consortium: Eiffage Génie Civil (lead contractor) / Razel-Bec Roussillon for Hyd'Occ (Qair France - Qair Group and AREC Occitanie).
-
15.10.2024In Côte d'Ivoire, the final adjustments to the Singrobo-Ahouaty...A look back in pictures at the final adjustments to the Singrobo-Ahouaty hydroelectric dam in Côte d'Ivoire, a 1,400-meter-long structure with a reservoir capacity...
-
04.10.2024Norway: Bjønnås twin-tube tunnel completedFreeway E18-lot 2 | In Norway, excavation of the Bjønnås twin-tube tunnel is now complete! Crews have excavated nearly 450,000 m3 of rock, some of which will be...
-
12.09.2024Latest updates on Line C of the Toulouse MetroThe tunnel boring machine has been inaugurated, Saint Barbara statues have been installed, and excavation has begun... a recap of the latest key milestones on this...