The final tunnel boring machine, Lise Enjalbert, has left Eiffage's refurbishment workshop in Thieux (77) to be transported to Toulouse. It will excavate the section from Ponts Jumeaux Station to the Laporte Shaft (4.2 km).
The tunnel boring machine Jeanne Marvig, which began excavation of the 4 km section from Colomiers Gare Shaft to the Laporte Shaft in early September, continues its progress towards Colomiers Gare Station to complete its first breakthrough before the end of the year.
After being christened on Thursday, October 31, following the tradition so cherished by our teams at the future La Vache Station, the tunnel boring machine Berthe de Puybusque began its underground journey to cover 2.5 km from La Vache - Le Grand Marché Station to Ponts-Jumeaux Station.
The excavation of the 460 m gallery using the traditional method began during the summer, with two approaches from Sept Deniers – Stade Toulousain Station and the Atelier Daturas Sud garage shaft. This gallery will enable the delivery of trains to the Line C garage workshop, where maintenance operations will be carried out.
Group of companies: Eiffage Génie Civil (lead contractor) – NGE - BTP
For Tisséo Ingénierie Tisséo Collectivités
Credit: MXR Communication
-
11.12.2024In Norway, Eiffage Génie Civil has completed the breakthrough...On the E18 | Lot 2 project, our Eiffage Génie Civil teams completed the breakthrough of the Grenland tunnel (2 x 5.1 km), with the attack and counter-attack meeting...
-
27.11.2024In Togo, Eiffage Génie Civil Marine has been entrusted...Lome Container Terminal has entrusted the deepening works of the main quay at the Port of Lomé to the teams of Eiffage Génie Civil Marine and Eiffage in Togo.
-
19.11.2024In Colombia, on the Puerto Antioquia project, 650 piles...A new milestone has been reached: the 650th pile has been driven!